AVK, one of Europe’s largest power solution providers for data centres, faced the complex challenge of supplying 24 MTU 2750 kVA emergency standby diesel generator systems to a hyperscale data centre in Italy, in 4 phases of 6 units each.

They required an acoustic enclosure manufacturer with the capabilities and capacity to design, manufacture, and fully fit-out a bespoke acoustic enclosure for each of the 24 generator sets. The enclosures needed to meet strict noise level requirements of 85 dB(A) at 1 metre, whilst also adhering to tight deadlines and stringent quality standards.

By choosing to partner with ADE, AVK leveraged a single-source approach to achieve precision engineered designs, consistent quality, and seamless project delivery. Working alongside AVK, ADE ensured the successful delivery of all 24 fully packaged solutions on schedule, meeting regulations and client expectations.

ADE Power Spider Logo

Industry:

ADE Power Spider Logo

The Situation

AVK was contracted to deliver 24 MTU 2750 kVA emergency standby generator systems in 4 phases of 6 units each to a hyperscale data centre in Italy. These generators needed to be housed in bespoke acoustic enclosures attenuated to a stringent noise level of 85 dB(A) at 1 metre. Each enclosure also had to accommodate internal auxiliary equipment, including fuel day tanks, lube oil tanks, control link boxes, and lighting systems.

Key challenges included developing custom designs that adhered not only to the project's rigorous technical specifications, but also to demanding site regulations. Additionally, the first phase required an expedited turnaround, with the first 6 enclosures needing complete mechanical and electrical fit-out within just 3 days. Consistent quality and on-schedule delivery across all 24 units were non-negotiable for this high-stakes project, which demanded meticulous project management and quality assurance.

ADE Power Spider Logo

Our Solution

ADE employed a comprehensive approach to address both AVK’s and the end client’s requirements, ensuring the successful execution of each phase of the overall project.

Design & Engineering

Our in-house engineering team designed the bespoke acoustic solutions using the latest 3D design software, ensuring complete accuracy and compliance with the specification. The enclosure spec was precisely tailored for the MTU DS2750 generator set to meet noise reduction requirements.

Fabrication & Paint

Our experienced team of fabricators and painters then manufactured and painted the enclosures, each measuring 13.9 metres in length, 2.9 metres in width, and 3.4 metres in height. Alongside the enclosures, our teams also manufactured and painted 24 1,000 litre fuel day tanks to meet the project specification.

Full Mechanical & Electrical Fit-Out

Our mechanical and electrical fit-out teams installed the MTU generators into the enclosures, alongside the fuel day tanks with duty / standby fuel pumps, load cable internal link boxes, lube oil tanks, external control link boxes, other auxiliary equipment, and small light and power. To meet the tight deadline for the first 6 units, our fit-out teams worked in 24 hour shifts, successfully completing the units to meet AVK’s timeline. Rigorous quality control was conducted at each stage throughout to ensure adherence to all the required safety and environmental standards.

Project Management

From design through to dispatch, our project management and quality assurance teams ensured seamless execution, minimising risks and delivering consistent results. As a single-source supplier for all the enclosures for this project, ADE reduced AVK’s supply chain complexity and the need to coordinate between multiple vendors to ensure product quality and consistency.

ADE Power Spider Logo

The Results

The successful partnetship between AVK and ADE delivered the following significant outcomes:

  • On-Time Delivery: All 24 packaged generator units were handed over to AVK on schedule, enabling them to meet critical project milestones.
  • Consistent Quality: In choosing ADE, AVK's single-source approach ensured uniform high quality across all units, reducing risks of defects or inconsistencies.
  • Regulatory Compliance: All enclosures were manufactured to meet stringent site regulations, particularly achieving the required noise level of 85 dB(A) at 1 metre.
  • Simplified Project Management: AVK benefitted from streamlined coordination by partnering exclusively with ADE, enhancing efficiency and reducing potential points of failure.
  • Enhanced Supply Chain Efficiency: ADE managed the complete end-to-end process of manufacturing and packaging the enclosures, providing a comprehensive solution from design to fit-out.
  • Excellent Performance: The acoustic treatment and integration of all equipment and systems resulted in dependable emergency power systems for the hyperscale data centre.

This example of yet another successful collaboration between ADE and AVK exemplifies how a strategic partnership can overcome complex challenges, deliver exceptional results, and ensure client satisfaction. With bespoke designs, precision manufacturing, meticulous project management, and laser-focused quality assurance, this project represents a benchmark for excellence in delivering critical infrastructure for the ever-growing hyperscale data centre industry.

To learn more about how we can support your power generation packaging needs, or to discuss a potential project, contact us today.

Acoustic Enclosures  Data Centre Equipment Packaging Solutions 

Share this case study:

For more information about our bespoke acoustic enclosure solutions

Get in touch to speak with our experts